Fire-damaged LNG plant in Norway to remain closed for up to a year

Fire-damaged LNG plant in Norway to remain closed for up to a year

In addition to damages caused by the fire on the air intake on one of the plant’s five power turbines, large amounts of seawater from the extinguishing have damaged other auxiliary systems such as electrical equipment and cables in the plant.

The duration of the shutdown will depend on the delivery time of necessary equipment.

Progress will also be affected by the current restrictions related to the Covid-19 virus, Equinor said.

Plant director Andreas Sandvik said: “Safety is the first priority and we will not start the plant until we are sure that it can be done in a safe way. Therefore, we have worked systematically and thoroughly to map the damage after the fire, and assess the technical condition of the plant.

“Although a lot of inspection work still remains and there is still significant uncertainty, our best estimate now is that that it may take up until 1 October 2021 to get Hammerfest LNG back into production.

“We will use the shutdown period to also carry out other maintenance and repair work planned for 2021. This includes both ongoing maintenance and maintenance planned in a planned turnaround next spring.”

Equinor, as well as the PSA and the police have started independent investigations of the fire.

Grete Haaland, senior vice president for Equinor’s onshore facilities, said: “The fire at Hammerfest LNG was a serious incident. The various investigations into the incident will be important in order to identify measures that will prevent similar incidents from happening again.”

 

Sourcewww.energyvoice.com

Leave a Reply

Your email address will not be published.